A drywall subcontractor in Gwinnett County is owed $58,400 on a 40-unit townhome building. On day 62, the office manager downloads a lien form, types in the name off the subcontract, and heads for the courthouse. Nobody caught that title moved mid-project to a new single-purpose LLC formed by the same developer under a nearly identical name. Recorded as drafted, that document names a stranger to title — and after day 90 the error cannot be cured.
The surrounding statutory system is covered in our complete guide to Georgia mechanics liens. This article is the mechanical work: preparing the claim of lien, recording it correctly, serving it in the right window, and avoiding the defects that destroy valid claims.
Two Confirmations Before You Record
Confirm You Are in a Statutory Category
Georgia does not give lien rights to everyone owed money. O.C.G.A. § 44-14-361 lists ten categories of special lien claimant: mechanics; contractors, subcontractors, materialmen, and laborers; registered architects, foresters, land surveyors, professional engineers, and interior designers; factory construction and machinery contractors and suppliers; machinists and machinery manufacturers; railroad construction contractors; and suppliers of rental tools, machinery, and equipment. Confirm your fit first.
Confirm the Amount You Can Properly Claim
The lien covers the amount due and owing under the express or implied contract, subcontract, or purchase order, plus interest on the principal. Reconcile the contract, change orders, and pay applications against payments made. Amounts you feel morally owed — inefficiency, delay, unauthorized extras — are not automatically due under the contract. And the owner is not required to pay more than the contract price of the improvement, as the pillar guide explains.
Identifying the Property and the Owner Correctly
An hour of research prevents the most common document defect.
Legal Description Versus Street Address
A street address identifies a mailing destination; a legal description identifies land in the deed records. The lien attaches to a parcel, so the description should come from the recorded instrument that vested title — typically the most recent deed — not a subcontract cover page. On subdivided projects, lot and block references matter: describing the whole tract when your work touched three lots gives the other side a free argument.
Single-Purpose Entities and Ownership That Changed Mid-Project
Developers hold projects in individual LLCs, and those entities get created, renamed, merged, and replaced during a build. The name on your subcontract is the party you contracted with, not evidence of who holds title today. Check the tax parcel record and the deed records close to the day you record, not at the start of the job — both the document and the service step run to the owner of the property. Ground leases and landlord-tenant buildouts complicate this further: two distinct interests exist in the same dirt, and naming the wrong one invites an attack on the entire filing.
Fixing the Last Date of Work or Delivery
Under O.C.G.A. § 44-14-361.1, the claim of lien must be filed for record within 90 days after the work was completed or the materials were furnished. Everything downstream depends on that date, so treat it as a factual finding supported by documents.
What Establishes the Date
Signed and dated delivery tickets carrying a receiving signature. Daily field reports naming crew, area, and scope. Superintendent sign-off on a scope-complete form. Project time records, dated photographs, contemporaneous emails. What does not establish it: an invoice date chosen by accounting, or a foreman’s memory.
Why Punch List and Warranty Trips Get Contested
Claimants want the last site trip to be the last day of work. Owners argue that punch list corrections, warranty repairs, and return trips to fix your own defective work are not new work furnished under the contract. Both positions get litigated. Calculate from the conservative date — substantial completion of your scope — and treat any later date as a fallback, never the plan.
What a Properly Prepared Claim of Lien Identifies
As practice guidance rather than a statutory form: a properly prepared claim of lien identifies the claimant by its correct legal name and the capacity in which it claims — contractor, subcontractor, materialman, equipment lessor. It identifies the owner, and the property by a legal description sufficient to locate it. It states the amount claimed, the contract or purchase order it rests on, the party the claimant contracted with, and the dates, including the date the work was completed or materials furnished. It is signed and in recordable form.
Recording and Serving: the Sequence
- Establish the last date of work from documents; calendar day 90.
- Pull current title and the legal description from the deed records.
- Reconcile the amount claimed to the contract and to payments made.
- Prepare and sign the claim of lien.
- File it for record, within the 90 days, with the clerk of the superior court of the county where the property is located.
- Within two business days after filing, send a true and accurate copy to the owner by registered or certified mail or statutory overnight delivery.
- Docket the 365-day deadline to sue and the 30-day notice deadline after that.
The Right County, and Why Re-Recording Does Not Fix It
The filing goes in the county where the property sits — not where your office is, not where the general contractor is headquartered. Metro Atlanta makes this easy to get wrong: a jobsite can sit feet from a county line while the developer’s address is elsewhere. Recording in the wrong county does not stop the 90-day clock, and re-recording correctly after day 90 restores nothing.
The Two-Business-Day Service Step
Section 44-14-361.1 requires that no later than two business days after the claim of lien is filed of record, a true and accurate copy be sent to the owner by registered or certified mail or statutory overnight delivery. True and accurate means the recorded version, with whatever the clerk stamped on it — not the draft on the desktop. Business days are not calendar days, so filing before a holiday weekend buys no thinking time. Proof of mailing belongs permanently in the file; compliance may be litigated a year later.
Document Defects That Void or Cripple Liens
- Naming an entity that does not hold title — a pre-transfer owner or similarly named affiliate.
- Describing the property by street address alone, or by a description that does not match the parcel.
- Recording in the wrong county.
- Miscalculating the last date of work and recording after day 90.
- Claiming an amount the contract or purchase order does not make due.
- Sending the owner the draft rather than the recorded document.
- Counting the two-business-day service window in calendar days.
- Keeping no proof of the mailing or overnight delivery.
- Signing in a trade name that is not the contracting party.
Overstating the Claim Is a Self-Inflicted Wound
There is an instinct to round up — the disputed extra, the delay cost, unearned retainage — on the theory that a bigger number creates more pressure. It creates more exposure. Padding invites an attack on the good faith of the whole filing and undercuts your position on O.C.G.A. § 13-6-11 litigation expenses, which must be specially pleaded with a prayer for relief and rest on bad faith, stubborn litigiousness, or unnecessary trouble and expense. Claim what the contract makes due, plus interest.
The Day After You Record
Title is clouded and people notice fast. Expect a call from the owner, from a general contractor that does not want a lien on its job, or from a closing attorney who cannot fund a closing. That leverage is the point — and it is where claimants lose, because negotiating is comfortable and 365 days feels long. Under § 44-14-361.1 you must commence an action within 365 days from the date of filing for record, and within 30 days after commencing it file a notice with the clerk of the superior court of the county where the lien was filed. Both are mandatory; failure renders the lien unenforceable.
What Filing Does Not Do
A recorded claim of lien does not collect money; it encumbers title and creates pressure. It does not replace your breach of contract claim — the lien runs against the property, the contract claim against your counterparty, and the two usually run together. And it does not extend a waiver’s fuse: under O.C.G.A. § 44-14-366, lien rights cannot be waived in advance of furnishing labor, services, or materials, and a statutory waiver becomes binding on the earliest of actual receipt of funds, a written acknowledgment of payment, or 90 days after execution unless the claimant first files an affidavit of nonpayment in the county where the property is located.
Frequently Asked Questions
Can I file a mechanics lien in Georgia without an attorney?
Nothing requires a lawyer, and plenty of contractors record liens themselves. The question is whether the document survives contact with opposing counsel. The failures are not exotic: the wrong owner entity, a description from the wrong source, an unsupportable last-date-of-work calculation, service on day three. Because the deadlines in O.C.G.A. § 44-14-361.1 are mandatory and failure renders the lien ineffective, an hour of review is cheap against the amount at stake.
What happens if I file my Georgia mechanics lien in the wrong county?
The statute directs the filing to the clerk of the superior court of the county where the property is located, so a lien recorded elsewhere is not in the records that matter. Re-recording correctly helps only if days remain on the 90 — filing in the right county on day 94 does not rescue a wrong-county filing on day 80.
Do I need a notice of commencement to file a lien in Georgia?
No. The system under O.C.G.A. § 44-14-361.5 imposes obligations; it does not create your lien right. It requires a notice of commencement filed not later than 15 days after the contractor physically commences work, and requires a claimant with no direct contract with the contractor to notify both owner and contractor within 30 days of the later of that filing or its first delivery. It also provides that the failure to file a notice of commencement renders that Code section inapplicable — a separate track, covered in the pillar guide.
Talk to Us Before the Document Goes to the Courthouse
Howe & Associates, P.C. has represented creditors in Atlanta since 1985. We prepare and record claims of lien, handle the service step and the deadline chain, and pursue the underlying contract claim in the right forum — noting that magistrate court jurisdiction under O.C.G.A. § 15-10-2(a)(5) reaches only $15,000.00, with no prejudgment attachment and no equitable relief. Inside your 90 days? Call (404) 219-7800.
This article is general information about Georgia law and is not legal advice; no attorney-client relationship is created by reading it.
This article is general information about Georgia law and is not legal advice. No attorney-client relationship is created by reading it.