In Georgia, a Notice of Commencement is a document the owner, the owner’s agent, or the general contractor files with the superior court clerk within 15 days after the contractor physically starts work, and posts on the job site. Once it is filed, subcontractors, suppliers, and others who do not have a contract directly with the general contractor must send a written Notice to Contractor within 30 days of the later of the filing or their first delivery to the property to make good their lien rights.
That 30-day notice is easy to miss because it comes at the start of a job, long before anyone expects a payment problem. Below we cover what O.C.G.A. § 44-14-361.5 requires and how it fits with the later deadlines in § 44-14-361.1.
Why the Notice of Commencement Matters to Subs and Suppliers
Georgia gives special liens on real property to contractors, subcontractors, materialmen supplying subcontractors, laborers, suppliers of rental equipment, and others who improve it (O.C.G.A. § 44-14-361(a)). For parties further down the chain, there is an extra early step.
The Notice of Commencement triggers that step. It identifies the owner and contractor and where notices should go, and in exchange the law asks lower-tier parties, whom the owner may not know exist, to identify themselves early with a Notice to Contractor.
For a broader overview of how these liens work, see our complete guide to Georgia mechanics liens for contractors and suppliers.
The Notice of Commencement: Who Files It, When, and What It Says
Who files and when
Under O.C.G.A. § 44-14-361.5(b), the owner, the owner’s agent, or the contractor files the Notice of Commencement with the clerk of the superior court in the county where the project is located. The statute sets the timing at not later than 15 days after the contractor physically commences work on the property. A copy must also be posted on the project site.
The statute does not force any single party to file, and on many private projects no Notice of Commencement is ever filed. That has consequences discussed below.
Required contents
The statute lists what the Notice of Commencement must include:
- The name, address, and telephone number of the contractor
- The name and location of the project being constructed and the legal description of the property
- The name and address of the true owner of the property
- The name and address of the person, other than the owner, at whose instance the improvements are being made, if that person is not the true owner
- The name and address of the surety for the performance and payment bonds, if any
- The name and address of the construction lender, if any
For a subcontractor or supplier, this is useful on its own: it names the true owner, the bond surety, and the lender, all of which matter if you later file a lien or pursue a bond claim. Under subsection (e), the clerk indexes each notice under the names of the true owner and the contractor, so you can search county records by either name. Under subsection (d), filing does not create a cloud or encumbrance on title and does not affect loan priority or future advances.
The Notice to Contractor: The 30-Day Rule
Who must send it
O.C.G.A. § 44-14-361.5(a) applies to any person with a right to a lien under paragraphs (1), (2), and (6) through (9) of § 44-14-361(a) who does not have privity of contract with the contractor. In plain terms, if your contract is with a subcontractor, a supplier, or someone else below the general contractor, rather than with the general contractor itself, this rule likely applies to you. Typical examples include sub-subcontractors, suppliers to subcontractors, laborers working for subcontractors, and equipment rental companies supplying a subcontractor.
The deadline
The notice must be given within 30 days from the filing of the Notice of Commencement or 30 days following the first delivery of labor, services, or materials to the property, whichever is later. For example:
- If the Notice of Commencement was filed on March 1 and you first delivered materials on April 10, your 30 days run from April 10.
- If you first delivered on March 1 and the Notice of Commencement was filed on March 12, your 30 days run from March 12.
Because the clock can start before you know a notice was filed, the safe practice is to send the Notice to Contractor promptly after first delivery on every job.
Who receives it and how
Under subsection (c), the notice goes to the owner or owner’s agent and to the contractor, at the addresses in the Notice of Commencement, by registered or certified mail or statutory overnight delivery.
What the Notice to Contractor must say
The statute requires the notice to include:
- The name, address, and telephone number of the person providing the labor, services, or materials
- The name and address of each person at whose instance the labor, services, or materials are being furnished (usually the subcontractor or other party who hired you)
- The name and location of the project as set out in the Notice of Commencement
- A description of the labor, services, or materials being provided and, if known, the contract price or anticipated value, or the amount claimed to be due
What Happens If You Do Not Send the Notice
The statute frames the Notice to Contractor as a requirement “to make good” the covered liens. If a Notice of Commencement was properly filed and a non-privity claimant does not send a timely Notice to Contractor, the claimant generally risks losing the ability to enforce a lien on that project. Filing a claim of lien later will not cure the missed early notice in most situations.
Losing lien rights does not erase the debt, and you may still have contract claims against the party who hired you. But the lien reaches the property itself, which is why we treat the Notice to Contractor as routine. Whether a late or defective Notice of Commencement excuses the requirement is fact-specific, so it is better to send the notice than to argue later that it was not required.
What If No Notice of Commencement Was Filed?
Subsection (d) states that the failure to file a Notice of Commencement renders the provisions of § 44-14-361.5 inapplicable. In other words, if no Notice of Commencement is filed, the Notice to Contractor requirement in that section does not apply.
The claim-of-lien and lawsuit deadlines in § 44-14-361.1 still apply. And because a Notice of Commencement may be filed after you start, and records searches are not always reliable, sending the notice anyway costs little and removes the question.
Requesting a Copy of the Notice of Commencement
Subsection (b) gives subcontractors and suppliers a useful tool. The contractor must provide a copy of the Notice of Commencement to any subcontractor, materialman, or person who makes a written request. If the contractor fails to provide the copy within 10 calendar days after receiving the written request, § 44-14-361.5 does not apply to the person who asked.
A written request gets you the addresses you need and creates a record if the contractor does not respond. Keep a copy and note the date it was received.
How the Notice Rules Interact With the Lien Deadlines
The Notice to Contractor is a front-end step. The main lien deadlines come later under O.C.G.A. § 44-14-361.1(a), which requires substantial compliance with the contract, a claim of lien filed within 90 days after completing the work or furnishing materials, a copy sent to the owner within two business days of filing, and a lien action commenced within 365 days of filing the claim, with notice of the action filed within 30 days after commencing it.
The sections connect directly: § 44-14-361.1(a)(2) provides that if a Notice of Commencement was filed under § 44-14-361.5(b), the claimant must also send a copy of the claim of lien to the contractor at the address shown in the Notice of Commencement. So the Notice of Commencement matters twice.
Our article on Georgia mechanics lien deadlines covers the later timelines in more detail, and our step-by-step guide to filing a mechanics lien in Georgia explains the filing process itself.
| Step | Who | Timing (per statute) | Source |
|---|---|---|---|
| File and post Notice of Commencement | Owner, owner’s agent, or contractor | Not later than 15 days after contractor physically starts work | § 44-14-361.5(b) |
| Provide copy of NOC on written request | Contractor | Within 10 calendar days of request | § 44-14-361.5(b) |
| Send Notice to Contractor | Non-privity lien claimants | Within 30 days of NOC filing or first delivery, whichever is later | § 44-14-361.5(a), (c) |
| File claim of lien | Lien claimant | Within 90 days after completion of work or furnishing materials | § 44-14-361.1(a)(2) |
| Send copy of claim of lien | Lien claimant | Within 2 business days of filing (to owner, and to contractor if NOC filed) | § 44-14-361.1(a)(2) |
| Commence lien action | Lien claimant | Within 365 days of filing claim of lien | § 44-14-361.1(a)(3) |
A Practical Day-One Checklist for Subcontractors and Suppliers
- Get project information up front. Ask for the owner, general contractor, property address, and any payment bond.
- Check county records. Search the project county’s superior court clerk records under the owner’s and contractor’s names.
- Request a copy in writing. If you cannot find one, send the contractor a written request and calendar the 10-day mark.
- Send the Notice to Contractor on every job. Send it promptly after first delivery, by certified mail or statutory overnight delivery, to both the owner and the contractor.
- Calendar the later deadlines. Track your last date of work or delivery so the 90-day claim-of-lien window does not slip by.
- Keep proof. File the notice, mailing receipts, and delivery tickets together.
Learn more about how our firm handles mechanics liens for Georgia contractors and suppliers.
Frequently Asked Questions
Is a Notice of Commencement required on every Georgia project?
The statute allows the owner, the owner’s agent, or the contractor to file one, within 15 days after the contractor physically starts work, but many private projects never have one filed. If none is filed, the statute says § 44-14-361.5 does not apply. The other lien requirements in § 44-14-361.1 still apply either way.
Do I need to send a Notice to Contractor if I contract directly with the general contractor?
Generally, no. Section 44-14-361.5(a) applies to lien claimants who do not have privity of contract with the contractor. If your contract is directly with the general contractor, you are in privity. Sub-subcontractors, suppliers to subcontractors, and similar lower-tier parties are the ones the rule targets.
When does the 30-day Notice to Contractor period start?
It runs from the later of two dates: the filing of the Notice of Commencement or your first delivery of labor, services, or materials to the property. Because it is easy to misjudge when a notice was filed, many suppliers send the Notice to Contractor right after first delivery on every job.
How do I send a Notice to Contractor?
The statute requires registered or certified mail or statutory overnight delivery to the owner or the owner’s agent and to the contractor, at the addresses in the Notice of Commencement. The notice must identify you, the party who hired you, the project as named in the Notice of Commencement, and the work or materials and their value or amount due.
Talk to a Georgia Collection Attorney
If you supply labor, materials, or equipment on Georgia construction projects and are facing nonpayment, our firm can review your notices, deadlines, and lien options. Call us at (404) 219-7800 or submit your claim online to discuss your situation.
This article is general information about Georgia law, not legal advice, and reading it does not create an attorney-client relationship. Laws change, and every claim turns on its own facts. Contact our firm to discuss your specific situation.
This article is general information about Georgia law and is not legal advice. No attorney-client relationship is created by reading it.