A plumbing subcontractor on a Cobb County build-out finished its last work on a Thursday and recorded a claim of lien on day 88 — deadline met, the file note said. Recording went through late on a Friday; the owner’s copy went out the following Tuesday, because Monday was busy. By the time owner’s counsel responded, the sub was arguing not about payment but about how to count two business days from a Friday recording.
One File, Seven Clocks
Contractors talk about “the lien deadline,” singular. Georgia’s statutes set several, starting on different events and often running at once, each able to end the claim by itself. Our complete guide to Georgia mechanics liens covers who holds lien rights and what the lien secures; this article covers only the calendar. In order:
- 15 days after the contractor physically commences work — the notice of commencement.
- 30 days from the later of that filing or first delivery — notice from a claimant with no direct contract with the contractor, to both owner and contractor.
- 90 days from execution of each waiver and release, after which it binds.
- 90 days after the work was completed or the materials were furnished — the claim of lien.
- Two business days after the lien is filed of record — the owner’s copy.
- 365 days from the date of filing for record — commence the action.
- 30 days after commencing it — notice of the action in the lien county.
Clocks one and two come from O.C.G.A. § 44-14-361.5, the waiver clock from O.C.G.A. § 44-14-366, and the last four from O.C.G.A. § 44-14-361.1, whose requirements are mandatory: failure renders the lien ineffective or unenforceable.
The Upstream Clocks
Notice of Commencement: 15 Days After Work Physically Begins
Under O.C.G.A. § 44-14-361.5, the notice of commencement is filed not later than 15 days after the contractor physically commences work on the property, with the superior court clerk in the county of the project. The trigger is physical commencement, not contract execution. The section adds that “the failure to file a notice of commencement shall render the provisions of this Code section inapplicable,” so locating it belongs at the front of a file.
Notice to Contractor: 30 Days From the Later of Two Dates
A party furnishing labor, services, or materials without a direct contract with the contractor must send written notice to both the owner and the contractor within 30 days from the later of (a) the notice of commencement filing date or (b) the date it first delivered labor, services, or materials to the property.
Claimants get “later of” wrong in both directions. Notice filed March 5, first delivery March 20: the 30 days run from March 20. Reverse it — first delivery February 26, notice filed March 5: the filing is later, so the 30 days run from March 5. Counting always from your own delivery loses the second case; counting always from the notice loses the first.
The 90-Day Filing Clock
What Actually Starts It
O.C.G.A. § 44-14-361.1 requires the claim of lien to be filed within 90 days after the work was completed or the materials were furnished, in the county where the property is located. Read that literally: not the invoice date, not the payment due date, not the last promise of a check. Those all fall later than the real trigger, which is why relying on them kills liens.
Punch List, Warranty Callbacks, and Return Trips
The most litigated timing question in Georgia lien practice is whether a late return to the site moved the completion date. Punch list work, a warranty callback, a trip to correct someone else’s damage — none has an across-the-board answer. Whether a return trip counts as completion is fact-dependent: what the contract required, what remained undone versus what was repaired, whether the work was contractual or a courtesy.
The Evidence That Fixes the Date
Daily reports, signed field tickets, delivery receipts, dated photos, and inspection sign-offs fix a date; a spreadsheet entry made months later does not. How a supplier dates its last delivery on a phased job is likewise fact-dependent.
The Two-Business-Day Service Clock
After the claim of lien is filed of record, a copy must go to the owner no later than two business days after filing, by registered or certified mail or statutory overnight delivery. It is the shortest deadline in the system and the most frequently blown, because the clock starts on recording, not on preparation, and recording often happens without the claimant’s office hearing that day. Have the owner’s copy addressed before the lien is submitted.
The 365-Day Suit Clock
The action must be commenced within 365 days from the date of filing for record of the claim of lien. Note the measuring point: the recording date — not the last day of work, not the day the 90-day period expired. Two claimants who finished the same day but recorded three weeks apart have deadlines three weeks apart.
A year feels generous, and it is the deadline creditors miss most often after the two-day one. Negotiation eats it: pay applications get resubmitted, a partial payment lands at month nine and resets everyone’s optimism. None of that stops the clock, nor does an acknowledgment of the balance. Review the file at day 270 and decide by day 300.
The 30-Day Notice-of-Action Clock
Suit is not the end of the sequence. Within 30 days after commencing the action, notice of that action must be filed with the clerk in the county where the lien was filed — a separate filing, in a specific county. The trap is geographic: when the case is pending outside the lien county, counsel’s attention sits in the forum while the obligation sits in the land records.
The Waiver Clock: 90 Days From Execution, One Per Waiver
O.C.G.A. § 44-14-366 provides that lien rights may not be waived in advance of furnishing labor, services, or materials. What it allows is a waiver and release binding upon the earliest of three events: actual receipt of funds, a separate written acknowledgment of payment, or 90 days after the date of execution of the waiver and release. Read the third again — it binds on day 90 whether or not a dollar arrived. The only escape: before that period expires, the claimant files an affidavit of nonpayment in the county where the property sits, suspending the waiver until full payment is received.
Now, monthly billing. A subcontractor signing a waiver with each pay application runs a rolling series of these clocks; a claimant three months behind may have three waivers binding on three different dates. Track them by execution date, not by the payment they were meant to accompany.
The Clocks That Survive a Blown Lien
Losing the lien is not losing the debt. The lien is security; the debt beneath it lives far longer. A simple written contract is governed by O.C.G.A. § 9-3-24, six years from when the amount became due and payable; open accounts and implied promises by O.C.G.A. § 9-3-25, four years. Neither is affected by a missed lien date. The lien under O.C.G.A. § 44-14-361 secures the amount due under the contract, subcontract, or purchase order plus interest, but the contract claim stands alone — and litigation expenses under O.C.G.A. § 13-6-11 may be sought, specially pleaded with a prayer for relief.
Nor does the clock stop at judgment. Under O.C.G.A. § 9-12-60, a judgment becomes dormant when seven years elapse after rendition without execution issued. Dormancy is prevented by entry on the general execution docket, an officer’s entry recorded by the clerk, or written notice of a bona fide public effort to enforce — each restarting a new seven-year period.
A Timing Checklist for a Live File
- Was a notice of commencement filed, and when? If none was, that Code section’s provisions are inapplicable.
- With no direct contract with the contractor, take the later of the notice date and your first delivery, and confirm notice reached both owner and contractor within 30 days.
- Log every executed waiver by execution date, flagged at day 75, so an affidavit of nonpayment reaches the property’s county before day 90.
- Fix the last date of unquestioned contract work or material, with documents proving it, and count 90 days from there.
- Address the owner’s copy before the lien is submitted; send it by registered or certified mail or statutory overnight delivery once recording is confirmed.
- Note the exact recording date and calendar the 365-day suit deadline from it.
- Calendar the notice of action in the lien county within 30 days of suit, even when the case is elsewhere.
- Calendar the contract limitations period separately.
Frequently Asked Questions
How long do I have to file a mechanics lien in Georgia?
Ninety days after the work was completed or the materials were furnished, filed with the clerk of the superior court of the county where the property is located, under O.C.G.A. § 44-14-361.1. The count runs from the work or the materials, not your invoice. Filing is only the first step: a copy must reach the owner no later than two business days after the lien is filed of record, and suit must be commenced within 365 days of that filing.
Does a promise to pay or a partial payment extend my Georgia lien deadline?
No. The 90-day filing clock runs from completion of the work or furnishing of the materials, and the 365-day suit clock from the date the claim of lien was filed for record. Neither is measured from correspondence, pay applications, or partial payments. Ongoing negotiation is the most common reason that deadline gets missed: the file feels active right up to the day enforcement is gone.
What happens if I miss the 90-day lien deadline in Georgia?
The lien is lost: the requirements of O.C.G.A. § 44-14-361.1 are mandatory, and failure renders the lien ineffective or unenforceable. What is not lost is the money owed: the contract claim continues under O.C.G.A. § 9-3-24 for simple written contracts, six years from when the amount was due and payable, or O.C.G.A. § 9-3-25 for open accounts and implied promises, four years.
Bring Us the Dates Before the Next Clock Runs
Howe & Associates, P.C. has represented creditors from Atlanta since 1985, and lien timing is cheap to fix early, expensive to fix late. If you have an uncertain last day of work, a waiver you were never paid on, or a lien nearing its enforcement date, send us the dates and we will tell you which clocks are still running. Call (404) 219-7800.
This article is general information about Georgia lien timing, not legal advice; the deadlines that apply to your project depend on its facts.
This article is general information about Georgia law and is not legal advice. No attorney-client relationship is created by reading it.